Stainton Oil Production Facility (28 MW wind farm)

Stainton Oil Production Facility is a 28 MW wind farm project in West Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 4 February 2009; the record was last updated on 4 February 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28 MWwind farm
application withdrawnstatus in REPD
4 February 2009record last updated
West Lindseycouncil area

Planning timeline

DateStage
19 January 2004Application submitted
4 February 2009Application withdrawn

Project details

Technology
wind farm
Capacity
28 MW
Status (REPD)
application withdrawn
Record last updated
4 February 2009
Operator or applicant
Star Energy
Planning authority
West Lindsey
Planning application reference
M03/p/1293
Turbines
14
Address (REPD)
Stainton Oil Production Facility , Ashing Lane , Dunholme
Council area (by location)
West Lindsey
REPD reference
3199

Who decides

ApplicationsWest LindseyUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused3 of 2112%
Onshore wind refused3 of 345%
Battery storage refused1 of 216%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Barfield Lane, Reephambattery storage53application submitted5.4
Fiskerton Airfield (Phase 1)solar farm12operational5.9
Fiskerton Airfield (Phase 2)solar farm22operational5.9
The Old Airfield Solar Photovoltaic Farmsolar farm49.9approved, not built6.5
RAF Faldingworthsolar farm40permission expired6.8
Springwell Solar Farm & Battery Storagesolar farm800approved, not built8.8
Middle Streetsolar farm20refused on appeal9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2962, -0.4184).