Fiskerton Airfield (Phase 2) (22 MW solar farm)

Fiskerton Airfield (Phase 2) is a 22 MW solar farm project in West Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2015; the record was last updated on 17 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWsolar farm
operationalstatus in REPD
17 September 2018record last updated
West Lindseycouncil area

Planning timeline

DateStage
7 November 2013Application submitted
30 January 2014Planning permission granted
1 October 2014Construction started
1 March 2015Operational

Project details

Technology
solar farm
Capacity
22 MW
Status (REPD)
operational
Record last updated
17 September 2018
Operator or applicant
Lark Energy
Planning authority
West Lindsey
Planning application reference
130671
Site area
68.8 ha
Address (REPD)
Reepham Road, Fiskerton, Lincoln
Council area (by location)
West Lindsey
Time to decision
12 weeks
REPD reference
5118

Who decides

ApplicationsWest LindseyUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused3 of 2112%
Onshore wind refused3 of 345%
Battery storage refused1 of 216%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fiskerton Airfield (Phase 1)solar farm12operational<0.1
The Old Airfield Solar Photovoltaic Farmsolar farm49.9approved, not built0.8
Barfield Lane, Reephambattery storage53application submitted1.3
Stainton Oil Production Facilitywind farm28application withdrawn5.9
Springwell Solar Farm & Battery Storagesolar farm800approved, not built6.1
Branston Solar Park (extension)solar farm40under construction7.1
Branston solar parksolar farm18.9operational7.6
Middle Streetsolar farm20refused on appeal8.4
Leverton Farm Energy Barnbattery storage10operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2439, -0.4287).