Middle Street (20 MW solar farm)

Middle Street is a 20 MW solar farm project in West Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 10 September 2015; the record was last updated on 5 October 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
refused on appealstatus in REPD
5 October 2015record last updated
West Lindseycouncil area

Planning timeline

DateStage
30 June 2014Application submitted
17 November 2014Refused by the planning authority
12 February 2015Appeal lodged
10 September 2015Appeal refused

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
refused on appeal
Record last updated
5 October 2015
Operator or applicant
RGE Energy UK
Planning authority
West Lindsey
Planning application reference
131496
Appeal reference
APP/N2535/W/15/3004150
Address (REPD)
Middle Street, Burton, Lincoln
Council area (by location)
West Lindsey
Time to decision
20 weeks
REPD reference
2037

Who decides

ApplicationsWest LindseyUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused3 of 2112%
Onshore wind refused3 of 345%
Battery storage refused1 of 216%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Leverton Farm Energy Barnbattery storage10operational1.4
Birch Holt Solar Farmsolar farm20refused on appeal1.5
South Carltonsolar farm29application submitted1.9
Springwell Solar Farm & Battery Storagesolar farm800approved, not built3.2
Ferry Lane, Skellingthorpesolar farm20.2approved, not built5.0
Barfield Lane, Reephambattery storage53application submitted7.1
The Old Airfield Solar Photovoltaic Farmsolar farm49.9approved, not built8.1
Fiskerton Airfield (Phase 2)solar farm22operational8.4
Fiskerton Airfield (Phase 1)solar farm12operational8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2681, -0.548).