Highgate Lane, Normanby-By-Spital Solar Photovoltaic Farm (11 MW)

Highgate Lane, Normanby-By-Spital Solar Photovoltaic Farm is an 11 MW solar farm project in West Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 July 2025, not yet built; the record was last updated on 19 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11 MWsolar farm
approved, not builtstatus in REPD
19 February 2026record last updated
West Lindseycouncil area

Planning timeline

DateStage
13 June 2024Application submitted
24 July 2025Planning permission granted
24 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
11 MW
Status (REPD)
approved, not built
Record last updated
19 February 2026
Operator or applicant
Boultbee Brooks Renewables Walkford Moor Limited
Planning authority
West Lindsey
Planning application reference
WL/2024/00415
Site area
16.0 ha
Address (REPD)
Land off Highgate Lane, Normanby-by-Spital
Council area (by location)
West Lindsey
Time to decision
58 weeks
Contracts for Difference
AR7a
Name in REPD
Highgate Lane, Normanby-By-Spital - Solar Photovoltaic Farm
REPD reference
15113

Who decides

ApplicationsWest LindseyUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused3 of 2112%
Onshore wind refused3 of 345%
Battery storage refused1 of 216%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
RAF Faldingworthsolar farm40permission expired4.0
Hemswell Cliff Wind Farmwind farm25refused on appeal6.3
Solar Panels at Tillbridge Solar Farmsolar farm500approved, not built7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3779, -0.494).