Energy Projects Near You

Solar, wind and battery projects near London (NW2)

79 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NW2 (Brent): 5 are waiting for a planning decision, 68 approved but not yet running. The largest live scheme is Mill Hill National Grid Substation (49.9 MW battery storage, approved on 13 March 2023, not yet built), 6.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

79projects within 10 km
5awaiting a decision
68approved, not running
0operational

Projects within 10 km of NW2

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Premier Park Road - Photovoltaic Systemrooftop solarrooftop solar1.4approved, not built may be out of dateupdated Mar 2022Mar 2022granted May 2022Mar 2022Brent4.3
Unit F, 6, Premier Park Roadrooftop solarrooftop solar1.3approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Brent4.3
Westfield London Shopping Centre, Ariel Wayrooftop solarrooftop solar1application submitted may be out of dateupdated Jul 2023Jun 2023—Jul 2023Hammersmith and Fulham5.6
Mill Hill National Grid Substationbattery storagebattery storage49.9approved, not builtupdated Mar 2023Sep 2020granted Mar 2023Mar 2023Barnet6.6
Pegasus House, Sackville Streetrooftop solarrooftop solar2.3approved, not built may be out of dateupdated Dec 2021Nov 2021granted Dec 2021Dec 2021Westminster7.9
Smaller schemes under 1 MW, mostly rooftop solar (60)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Willesden Sports Centre, Donnington Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Brent2.2
Ikea Department Store, Drury Way Solar Pv Canopiessolar farmsolar farm0.7approved, not builtupdated Nov 2023Aug 2023granted Oct 2023Nov 2023Brent2.8
West Hendon Estate, Plots A, C & G - 350 Apartments & Commercial Unitsrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Apr 2023granted Aug 2024Mar 2025Barnet2.9
Henderson Court, Fitzjohns Avenuerooftop solarrooftop solar0.2approved, not built may be out of dateupdated Nov 2022Aug 2022granted Nov 2022Nov 2022Camden3.0
Moberly Sports Centre - Photovoltaic Arraysrooftop solarrooftop solar0.2approved, not builtupdated Nov 2021Nov 2021granted Dec 2021Nov 2021Brent3.1
Moberly Sports Centre - Photovoltaic Arraysrooftop solarrooftop solar—refusedupdated Oct 2021Oct 2021refused Oct 2021Oct 2021Brent3.1
Kern House, Scrubs Lanerooftop solarrooftop solar—approved, not builtupdated Sep 2023Aug 2023granted Sep 2023Sep 2023Hammersmith and Fulham3.9
Rock Building, Waxlow Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2024Nov 2023granted Dec 2023Jan 2024Brent3.9
Premier Park Road, Units 20-23rooftop solarrooftop solar0.4approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Brent4.2
Central Wayrooftop solarrooftop solar—approved, not builtupdated Jul 2025Apr 2025granted May 2025Jul 2025Brent4.2
Premier Park Road, Unit 3rooftop solarrooftop solar0.6approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent4.2
Premier Park Road, Units 5-6rooftop solarrooftop solar0.4approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent4.2
Premier Park Road, Unit 9rooftop solarrooftop solar0.3approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent4.2
Premier Park Road, Units 10-11rooftop solarrooftop solar0.3approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent4.3
Bestway Cash and Carry, Abbey Roadrooftop solarrooftop solar0.4approved, not builtMay 2026granted May 2026—Brent4.3
Premier Park Road, Unit Arooftop solarrooftop solar0.4approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent4.3
Premier Park Road, Unit 7-8rooftop solarrooftop solar0.4approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent4.3
Premier Park Road, Unit 1rooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent4.3
Premier Park, Park Royalrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Brent4.3
Charlie Bighams, Mcnicol Driverooftop solarrooftop solar0.3approved, not builtupdated Jan 2024Dec 2023granted Feb 2024Jan 2024Brent4.3
Premier Park Road, Unit Erooftop solarrooftop solar0.4approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Brent4.4
Premier Park Road, Unit Crooftop solarrooftop solar0.5approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent4.4
Premier Park Road, Unit 4rooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent4.4
David Lloyd Leisurerooftop solarrooftop solar0.2refusedupdated Sep 2025Jul 2025refused Sep 2025Sep 2025Westminster4.4
Premier Park Road, Unit Brooftop solarrooftop solar0.6approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent4.4
Nucleus, Central Wayrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Aug 2023granted Oct 2023Nov 2023Brent4.5
Nucleus, Central Wayrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Brent4.5
Prop House, Abbey Roadrooftop solarrooftop solar0.6approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Brent4.5
Tudor Estate, Abbey Roadrooftop solarrooftop solar—application submittedupdated May 2026Apr 2026—May 2026Brent4.6
Hammersmith Hospital, Du Cane Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Mar 2025granted Jul 2025Aug 2025Hammersmith and Fulham4.7
Kensington Leisure Centre, Silchester Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Oct 2022granted Feb 2023Mar 2023Kensington and Chelsea4.9
Light House, Western Roadrooftop solarrooftop solar0.4approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024Ealing4.9
Ark Elvin Academy, Cecil Avenuerooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Jan 2024granted Mar 2024Jan 2024Brent4.9
Crompton Streetrooftop solarrooftop solar0.2approved, not builtupdated Dec 2021Oct 2021granted Nov 2021Dec 2021Westminster5.0
Unit 3, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Ealing5.0
Unit 4, Origin Business Park, Rainsford Roadrooftop solarrooftop solar1approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Brent5.0
Unit 2, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent5.0
Unit 1, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.7approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent5.1
London Zoo, Outer Circlerooftop solarrooftop solar0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Westminster5.1
Unit 6, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent5.2
Unit 5, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.6approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent5.2
Phoenix Fitness Centre, Phoenix Closerooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Hammersmith and Fulham5.2
Edwards Yard, Alperton - 581 Apartments & Commercial Unitsrooftop solarrooftop solar0.7approved, not builtupdated May 2022Sep 2020granted Jan 2022May 2022Brent5.4
Westfield London Shopping Centre, Ariel Wayrooftop solarrooftop solar0.3application submittedupdated Feb 2026Jan 2026—Feb 2026Hammersmith and Fulham5.7
Barnet Burnt Oak Leisure Centre, Watling Avenuerooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Barnet5.7
High Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2021Sep 2021granted Oct 2021Oct 2021Barnet5.9
David Lloyd Leisure Centre, Leisure Wayrooftop solarrooftop solar0.3approved, not builtupdated Feb 2024Dec 2023granted Jan 2024Feb 2024Barnet6.2
Ealing Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025Brent6.2
University College Hospital, Euston Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Nov 2022Sep 2022granted Nov 2022Nov 2022Camden6.9
London St Pancras International Station - Installation Of Solar Panelsrooftop solarrooftop solar—no application requiredupdated Mar 2025——Mar 2025Camden7.2
Waste & Recycling centre, Hornsey Streetrooftop solarrooftop solar0.4approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Islington7.2
Imperial College Health CentreSolar Panelsrooftop solarrooftop solar—application withdrawnupdated Apr 2021Feb 2021—Apr 2021Westminster7.4
Friern Barnet School, Hemington Avenuerooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Feb 2025granted Jul 2025Aug 2025Barnet7.9
Sainsburys Supermarkets, Essex Placerooftop solarrooftop solar0.3approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Hounslow7.9
The Queens Club, Palliser Roadrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Jun 2023Feb 2023granted May 2023Jun 2023Hammersmith and Fulham8.0
Devonhurst Placerooftop solarrooftop solar—approved, not built may be out of dateupdated Apr 2022Mar 2022granted May 2022Apr 2022Hounslow8.0
Mill Hill County High School, Worcester Crescentrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Barnet8.1
University Of West London Solar Photovoltaic & Ground Source Heat Pumprooftop solarrooftop solar0.2application withdrawnupdated Dec 2021Jul 2021—Dec 2021Ealing8.2
University Of West London Solarrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2021Jul 2021granted Nov 2021Dec 2021Ealing8.2
Fulham Pools, Lillie Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Jan 2024granted Apr 2024May 2024Hammersmith and Fulham8.2

14 more projects not listed (furthest or smallest).

Distance from the average position of the NW2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.7
Rooftop solar775660325.5
Battery storage1010049.9

MW in pipeline: pending, approved and under-construction capacity.

How Brent decides solar, wind and battery applications

ApplicationsBrentUK
Decided applications (solar, wind, battery)3910,236
Refused5 (13%)19%
Solar refused5 of 3912%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Brent

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NW2, 12 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.