Solar, wind and battery projects near Iona (PA76)
No solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of PA76 (Iona) in the Renewable Energy Planning Database (July 2026 extract). The nearest is Ionad Iomairt Thiriodh, Crossapol (0.1 MW solar farm, approved, not built), 35.0 km away.
35.0 kmto the nearest project
0projects within 10 km
0awaiting a decision
0approved, not running
0operational
The nearest recorded project is Ionad Iomairt Thiriodh, Crossapol, 35.0 km from the centre of PA76. Household rooftop panels and schemes below about 150 kW are not in the database.
How Argyll and Bute decides solar, wind and battery applications
| Applications | Argyll and Bute | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 22 (45%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 21 of 41 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 53.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 4 | — |