Renewable energy projects in Argyll and Bute

95 solar, wind or battery projects of 150 kW or more are located in Argyll and Bute (REPD, July 2026 extract): 20 pending, 16 approved but not running, 16 operational and 26 refused. The council refused 22 of 49 decided applications (45%; UK 19%), with a median 53 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

95projects in the council area
20awaiting a decision
16approved, not running
45%of decisions refused

How Argyll and Bute decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Projects in Argyll and Bute

Projects of 1 MW and more (86)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Cnoc Buidhe Windfarmwind farmwind farm191application submittedupdated Apr 2025Apr 2025—Apr 2025
Tullich Wind Farmwind farmwind farm180application withdrawnupdated Jun 2010Jun 2012—Jun 2010
Sheirdrim Renewable Energy Development Windwind farmwind farm114refused on appealupdated Jun 2023Oct 2019—Jun 2023
Cnoc Buidhe Windfarmbattery storagebattery storage109application submittedupdated Apr 2025Apr 2025—Apr 2025
Loch Awe - Eredine Wind Farmwind farmwind farm100application submittedupdated Dec 2024Nov 2024—Dec 2024
Corr Chnoc Wind Farmwind farmwind farm86.4application submittedupdated Mar 2025Mar 2025—Mar 2025
An Carr Dubh Wind Farmwind farmwind farm85.8application submitted may be out of dateupdated May 2023Mar 2023—May 2023
Blarghour Wind Farmwind farmwind farm84approved, not builtupdated Oct 2024May 2018granted Oct 2021Oct 2024
Tangy 4 Wind Farmwind farmwind farm80approved, not built may be out of dateupdated Aug 2025Sep 2018granted Dec 2019Aug 2025
Shira Wind Farmwind farmwind farm79application withdrawnupdated Aug 2012Mar 2006—Aug 2012
Narachan Wind Farmwind farmwind farm72.6refusedupdated Apr 2024Jan 2020refused Mar 2024Apr 2024
High Brenfield Wind Farmwind farmwind farm66application submittedupdated Jul 2025Jun 2025—Jul 2025
Wind Turbines at Allt Domhain Wind Farmwind farmwind farm64.8application submittedupdated Sep 2025Jul 2025—Sep 2025
Upper Sonachan Wind Farmwind farmwind farm64.6refused on appealupdated Jun 2019Oct 2015refused May 2019Jun 2019
Clachaig Glenwind farmwind farm60approved, not builtupdated Feb 2026Mar 2022granted Nov 2024Feb 2026
Cruach Brenfield Wind Farmwind farmwind farm59.4application withdrawnupdated Nov 2016May 2014—Nov 2016
Killean Wind Farmwind farmwind farm59.4application submittedupdated Oct 2024Aug 2024—Oct 2024
Ladyfield Renewable Energy Parkwind farmwind farm58.5approved, not builtupdated May 2025Jan 2024granted May 2025May 2025
High Constellation Wind Farmbattery storagebattery storage55.5approved, not built may be out of dateupdated Feb 2026May 2019granted Jun 2020Feb 2026
Creggan Wind Farmwind farmwind farm54refused on appealupdated Jun 2017Dec 2013refused Jun 2017Jun 2017
West Torrisdale Wind Farmwind farmwind farm54application submittedupdated Apr 2025Jan 2025—Apr 2025
Giants Burn Wind Farm-wind farmwind farm50.4application submittedupdated Oct 2025Jul 2025—Oct 2025
Ardencaple Farmbattery storagebattery storage50refusedupdated Nov 2024Mar 2024refused Oct 2024Nov 2024
Beinn an Tuirc Windfarm Phase 3wind farmwind farm49.9under constructionupdated May 2020Nov 2015granted Feb 2017May 2020
SSE Taynuilt Substationbattery storagebattery storage49.9approved, not builtupdated Dec 2025Dec 2024granted Nov 2025Dec 2025
Raera Forestwind farmwind farm48refusedupdated Sep 2012Dec 2009refused Nov 2015Sep 2012
Stacainwind farmwind farm48refused on appealupdated Feb 2013Apr 2005refused Dec 2005Feb 2013
High Constellation Wind Farmwind farmwind farm48approved, not built may be out of dateupdated Jul 2024May 2019granted Jun 2020Jul 2024
Black Craigwind farmwind farm47.5application withdrawnupdated Dec 2009——Dec 2009
Inverlieverwind farmwind farm47.5refusedupdated Nov 2015Nov 2002refused Aug 2005Nov 2015
Carraig Ghealwind farmwind farm46operationalupdated Oct 2017Nov 2004granted Jun 2008Oct 2017
Ardchonnel Wind Farmwind farmwind farm45refused on appealupdated Sep 2015Dec 2013refused May 2014Sep 2015
Cruach Clenamacrie Wind Farmwind farmwind farm45application submittedupdated Dec 2024Dec 2024—Dec 2024
Beinn an Tuirc Phase 2wind farmwind farm43.7operationalupdated Oct 2014Jul 2005granted Jul 2007Oct 2014
Corlarach Hillwind farmwind farm42refused on appealupdated Dec 2010Jun 2007refused Jan 2008Dec 2010
Alt Deargwind farmwind farm42refusedupdated Jan 2010Jun 2006refused Nov 2007Jan 2010
Ladyfield Renewable Energy Parkbattery storagebattery storage41.4approved, not builtupdated May 2025Jan 2024granted May 2025May 2025
Sheirdrim Renewable Energy Development Batterybattery storagebattery storage38refused on appealupdated Jul 2023Oct 2019—Jul 2023
Tangy Wind Farm - repowering/Tangy 3wind farmwind farm36.8permission expiredupdated Oct 2018Dec 2014granted Jun 2015Oct 2018
Blary Hill Wind Farmwind farmwind farm35operationalupdated Jan 2026Aug 2014granted Jun 2017Jan 2026
Beinn Ghlas Wind Farm - Repoweringwind farmwind farm33.6application submittedupdated Oct 2025Aug 2025—Oct 2025
Cruach Mhorwind farmwind farm33.3operationalupdated Jul 2004Sep 2001granted Jun 2002Jul 2004
Corriechreivewind farmwind farm30refusedupdated Apr 2007Apr 1995refused Dec 1995Apr 2007
Clachaig Glenbattery storagebattery storage30approved, not builtupdated Dec 2024Mar 2022granted Nov 2024Dec 2024
Drumfad Woodbattery storagebattery storage29.9permission expiredupdated Jul 2020Oct 2018granted Mar 2021Jul 2020
Beinn an Tuircwind farmwind farm29.7operationalupdated Jul 2013Apr 1998granted Apr 1999Jul 2013
Ardtaraig Wind Farmwind farmwind farm29.4refused on appealupdated Dec 2019Aug 2018refused Mar 2019Dec 2019
Allt Rubha Wind Farmwind farmwind farm27application withdrawnupdated Feb 2016Dec 2015—Feb 2016
Creag Dhubhwind farmwind farm27application submitted may be out of dateupdated Apr 2020Dec 2019—Apr 2020
Eascairt Wind Farmwind farmwind farm26approved, not builtupdated May 2020Feb 2015granted Sep 2018May 2020
Earraghail Renewable Energy Developmentbattery storagebattery storage25refusedupdated Apr 2025Feb 2022refused Feb 2025Apr 2025
Corr Chnoc Wind Farmbattery storagebattery storage25application submittedupdated Mar 2025Mar 2025—Mar 2025
Gartnagrenachwind farmwind farm24application withdrawnupdated Apr 2006——Apr 2006
Giants Burn Wind Farm -Batter Energy Storagebattery storagebattery storage23application submittedupdated Oct 2025Jul 2025—Oct 2025
Freasdail Wind Farmwind farmwind farm22.5operationalupdated May 2017Oct 2012granted Apr 2014May 2017
Largie Windfarm IIwind farmwind farm21refusedupdated Apr 2007Aug 2004refused Mar 2007Apr 2007
Cour Wind Farmwind farmwind farm20.5operationalupdated Apr 2018May 2010granted Oct 2012Apr 2018
Strone Saul Hillwind farmwind farm20refusedupdated Apr 2011Apr 2009refused Aug 2010Apr 2011
Sheirdrim Renewable Energy Development Solarsolar farmsolar farm20refused on appealupdated Jun 2023Oct 2019—Jun 2023
West Torrisdale Wind Farmbattery storagebattery storage20application submittedupdated Apr 2025Jan 2025—Apr 2025
Cruach Clenamacrie Wind Farmbattery storagebattery storage20application submittedupdated Dec 2024Dec 2024—Dec 2024
An Suidhewind farmwind farm19.3operationalupdated Jul 2020Aug 2005granted Oct 2005Jul 2020
Deucheran Hillwind farmwind farm15.8operationalupdated Aug 2019Jun 1999granted May 2001Aug 2019
Cnoc Donn Arniclewind farmwind farm15operationalupdated Feb 2010Apr 1998granted Apr 1999Feb 2010
Clachan Flats Wind Farmwind farmwind farm15operationalupdated Jul 2010May 2002granted Jul 2004Jul 2010
Largie Wind Farmwind farmwind farm14.9refusedupdated Aug 2004Aug 1994refused Nov 1998Aug 2004
Kilchattanwind farmwind farm13.6refused on appealupdated Mar 2012Jan 2008refused Mar 2011Mar 2012
Tangy Wind Farm/Tangy 1wind farmwind farm12.8operationalupdated Jan 2012Jun 2001granted Feb 2002Jan 2012
Cove Community Wind Farmwind farmwind farm11.5application withdrawnupdated Aug 2013Dec 2012—Aug 2013
Allt Dearg Wind Farmers LLPwind farmwind farm10.8operationalupdated Feb 2013Jan 2011granted Apr 2011Feb 2013
Ballygroggan Farmwind farmwind farm9refusedupdated Apr 2007Jul 1994refused Jul 1995Apr 2007
Clachan Seil Wind Farmwind farmwind farm8.1refusedupdated Feb 2013Feb 2012refused Nov 2012Feb 2013
Auchadaduie Wind Farmwind farmwind farm6.9operationalupdated Nov 2018Jan 2012granted Jul 2014Nov 2018
Tangy Wind Farm Extension/Tangy 2wind farmwind farm6operationalupdated Jan 2012Jul 2004granted Sep 2005Jan 2012
Srondoire Community Wind Farmwind farmwind farm6operationalupdated Apr 2016Jul 2013granted Dec 2013Apr 2016
Earraghail Renewable Energy Developmentsolar farmsolar farm5refusedupdated Apr 2025Feb 2022refused Feb 2025Apr 2025
Helensburgh Community Wind Farmwind farmwind farm4application withdrawnupdated Aug 2015Jul 2014—Aug 2015
A'Chruach (Phase 2)wind farmwind farm4permission expiredupdated Sep 2020Dec 2014granted Aug 2015Sep 2020
Laggan Windclusterwind farmwind farm3refusedupdated Oct 2011May 1995refused Jun 1999Oct 2011
Ascog Farm Wind Turbineswind farmwind farm2.7refused on appealupdated Jan 2014Oct 2012refused May 2013Jan 2014
Meall Mhor Wind Farmwind farmwind farm2.2application withdrawnupdated Jul 2004——Jul 2004
Cnocbreac Inver Estate Solar Generationsolar farmsolar farm2.1under constructionupdated Feb 2025Aug 2024granted Oct 2024Feb 2025
Tangy Farm Wind Turbinewind turbinewind turbine2application withdrawnupdated Dec 2014Nov 2012—Dec 2014
Hillcrest Farmwind farmwind farm1.7application withdrawnupdated Jun 2011Jul 2009refused Oct 2012Jun 2011
Stronafian Community Forest Wind Turbineswind farmwind farm1.6refusedupdated Sep 2016Jul 2015refused Aug 2016Sep 2016
Low Ugadale Farmwind farmwind farm1.5application withdrawnupdated Mar 2014Oct 2013—Mar 2014
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Marys Land, Tayvallich - Ground Mounted Solar Panelssolar farmsolar farm0.3application submittedupdated Apr 2026Mar 2026—Apr 2026
Rothesay Waste Water Treatmentsolar farmsolar farm0.3approved, not builtupdated Sep 2024Feb 2024granted Aug 2024Sep 2024
Glenegedale Lotts, Turbine Lottssolar farmsolar farm0.2approved, not builtupdated Jul 2024Feb 2024granted Jun 2024Jul 2024
Helensburgh Waste Water Treatment Works, Moss Roadsolar farmsolar farm0.2application submitted may be out of dateupdated Aug 2024Aug 2024—Aug 2024
Isle of Luing Wind Farmwind turbinewind turbine0.2permission expiredupdated Apr 2022Apr 2020granted Dec 2020Apr 2022
Ionad Iomairt Thiriodh, Crossapolsolar farmsolar farm0.1approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026
Gigha Wind Farm Battery Projectbattery storagebattery storage0.1decommissionedupdated Jul 2017——Jul 2017
Ardnadam Electricity Sub Station, Sandbankbattery storagebattery storage—approved, not built may be out of dateupdated Feb 2025Sep 2022granted May 2023Feb 2025
Loch Awe - Eredine Wind Farmbattery storagebattery storage—application submittedupdated Dec 2024Nov 2024—Dec 2024

Postcode districts in Argyll and Bute

DistrictProjects within 10 kmPendingApprovedOperational
G8413440
PA202010
PA210000
PA224001
PA2313340
PA241100
PA253120
PA264121
PA271100
PA289212
PA2910111
PA308102
PA315100
PA328331
PA334020
PA346400
PA358312
PA360000
PA374400
PA380000
PA415120
PA421010
PA432010
PA441000
PA450000
PA460000
PA470000
PA481000
PA490000
PA601010
PA610000
PA620000
PA630000
PA640000
PA653030
PA660000
PA670000
PA680000
PA690000
PA700000
PA713030
PA723030
PA730000
PA740000
PA750000
PA760000
PA772010
PA780000

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Argyll and Bute by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.