Energy Projects Near You

Srondoire Community Wind Farm (6 MW)

Srondoire Community Wind Farm is a 6 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 December 2015; the record was last updated on 4 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
operationalstatus in REPD
4 April 2016record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
10 July 2013Application submitted
11 December 2013Planning permission granted
20 June 2014Construction started
20 December 2015Operational

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
4 April 2016
Operator or applicant
Srondoire Wind Farmers LLP
Planning authority
Argyll and Bute
Planning application reference
13/01427/PP
Turbines
3
Address (REPD)
Cruach A Phubuill, Adj Allt Dearg Windfarm, Ardrishaig, Lochgilphead, Argyll, PA31 8PE
Council area (by location)
Argyll and Bute
Time to decision
22 weeks
REPD reference
4328

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Allt Dearg Wind Farmers LLPwind farm10.8operational0.2
Alt Deargwind farm42refused1.5
Allt Rubha Wind Farmwind farm27application withdrawn5.2
High Brenfield Wind Farmwind farm66application submitted6.7
Cruach Brenfield Wind Farmwind farm59.4application withdrawn7.2
Shira Wind Farmwind farm79application withdrawn9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9341, -5.4805).