Srondoire Community Wind Farm (6 MW)
Srondoire Community Wind Farm is a 6 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 December 2015; the record was last updated on 4 April 2016.
6 MWwind farm
operationalstatus in REPD
4 April 2016record last updated
Argyll and Butecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 10 July 2013 | Application submitted |
| 11 December 2013 | Planning permission granted |
| 20 June 2014 | Construction started |
| 20 December 2015 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 6 MW
- Status (REPD)
- operational
- Record last updated
- 4 April 2016
- Operator or applicant
- Srondoire Wind Farmers LLP
- Planning authority
- Argyll and Bute
- Planning application reference
- 13/01427/PP
- Turbines
- 3
- Address (REPD)
- Cruach A Phubuill, Adj Allt Dearg Windfarm, Ardrishaig, Lochgilphead, Argyll, PA31 8PE
- Council area (by location)
- Argyll and Bute
- Time to decision
- 22 weeks
- REPD reference
- 4328
Who decides
| Applications | Argyll and Bute | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 22 (45%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 21 of 41 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 53.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Allt Dearg Wind Farmers LLP | wind farm | 10.8 | operational | 0.2 |
| Alt Dearg | wind farm | 42 | refused | 1.5 |
| Allt Rubha Wind Farm | wind farm | 27 | application withdrawn | 5.2 |
| High Brenfield Wind Farm | wind farm | 66 | application submitted | 6.7 |
| Cruach Brenfield Wind Farm | wind farm | 59.4 | application withdrawn | 7.2 |
| Shira Wind Farm | wind farm | 79 | application withdrawn | 9.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9341, -5.4805).