Allt Dearg Wind Farmers LLP (10.8 MW)
Allt Dearg Wind Farmers LLP is a 10.8 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 September 2012; the record was last updated on 26 February 2013.
10.8 MWwind farm
operationalstatus in REPD
26 February 2013record last updated
Argyll and Butecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 17 January 2011 | Application submitted |
| 5 April 2011 | Planning permission granted |
| 1 December 2011 | Construction started |
| 25 September 2012 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 10.8 MW
- Status (REPD)
- operational
- Record last updated
- 26 February 2013
- Operator or applicant
- Ormsary and Stronachullin Estates (Allt Dearg Wind Farmers LLP)
- Planning authority
- Argyll and Bute
- Planning application reference
- 10/02151/PP
- Turbines
- 12
- Address (REPD)
- Cruach a'Phubuill, 9km south of Ardishaig, South Knapdale, Argyll
- Council area (by location)
- Argyll and Bute
- Time to decision
- 11 weeks
- REPD reference
- 3758
Who decides
| Applications | Argyll and Bute | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 22 (45%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 21 of 41 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 53.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Srondoire Community Wind Farm | wind farm | 6 | operational | 0.2 |
| Alt Dearg | wind farm | 42 | refused | 1.5 |
| Allt Rubha Wind Farm | wind farm | 27 | application withdrawn | 5.4 |
| High Brenfield Wind Farm | wind farm | 66 | application submitted | 6.7 |
| Cruach Brenfield Wind Farm | wind farm | 59.4 | application withdrawn | 7.2 |
| Shira Wind Farm | wind farm | 79 | application withdrawn | 10.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9334, -5.4774).