Cruach Brenfield Wind Farm (59.4 MW)

Cruach Brenfield Wind Farm is a 59.4 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 14 March 2016; the record was last updated on 30 November 2016. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

59.4 MWwind farm
application withdrawnstatus in REPD
30 November 2016record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
22 May 2014Application submitted
14 March 2016Application withdrawn

Project details

Technology
wind farm
Capacity
59.4 MW
Status (REPD)
application withdrawn
Record last updated
30 November 2016
Operator or applicant
Dulas
Planning authority
Scottish Government (S36)
Planning application reference
EC00002094
Turbines
18
Address (REPD)
forestry near to Ardrishaig in Argyll & Bute
Council area (by location)
Argyll and Bute
REPD reference
4356

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
High Brenfield Wind Farmwind farm66application submitted2.2
Allt Rubha Wind Farmwind farm27application withdrawn2.5
Shira Wind Farmwind farm79application withdrawn2.8
Alt Deargwind farm42refused5.8
Raera Forestwind farm48refused5.9
Srondoire Community Wind Farmwind farm6operational7.2
Allt Dearg Wind Farmers LLPwind farm10.8operational7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9984, -5.4786).