Allt Rubha Wind Farm (27 MW)

Allt Rubha Wind Farm is a 27 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 31 March 2016; the record was last updated on 5 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWwind farm
application withdrawnstatus in REPD
5 February 2016record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
15 December 2015Application submitted
31 March 2016Application withdrawn

Project details

Technology
wind farm
Capacity
27 MW
Status (REPD)
application withdrawn
Record last updated
5 February 2016
Operator or applicant
E.ON UK
Planning authority
Argyll and Bute
Planning application reference
15/03259/PP
Turbines
9
Address (REPD)
Land Approximately 6.5 Km To The South West Of Lochgilphead
Council area (by location)
Argyll and Bute
REPD reference
4334

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cruach Brenfield Wind Farmwind farm59.4application withdrawn2.5
High Brenfield Wind Farmwind farm66application submitted3.6
Alt Deargwind farm42refused4.1
Srondoire Community Wind Farmwind farm6operational5.2
Shira Wind Farmwind farm79application withdrawn5.2
Allt Dearg Wind Farmers LLPwind farm10.8operational5.4
Raera Forestwind farm48refused8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9798, -5.5002).