Energy Projects Near You

Solar, wind and battery projects near Lochgilphead (PA31)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA31 (Argyll and Bute): 1 is waiting for a planning decision. The largest live scheme is High Brenfield Wind Farm (66 MW wind farm, application submitted on 10 June 2025, no decision recorded), 6.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
1awaiting a decision
0approved, not running
0operational

Projects within 10 km of PA31

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Raera Forestwind farmwind farm48refusedupdated Sep 2012Dec 2009refused Nov 2015Sep 2012Argyll and Bute0.3
Shira Wind Farmwind farmwind farm79application withdrawnupdated Aug 2012Mar 2006—Aug 2012Argyll and Bute3.3
Cruach Brenfield Wind Farmwind farmwind farm59.4application withdrawnupdated Nov 2016May 2014—Nov 2016Argyll and Bute6.1
High Brenfield Wind Farmwind farmwind farm66application submittedupdated Jul 2025Jun 2025—Jul 2025Argyll and Bute6.9
Allt Rubha Wind Farmwind farmwind farm27application withdrawnupdated Feb 2016Dec 2015—Feb 2016Argyll and Bute8.5

Distance from the average position of the PA31 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm5100166

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.