Energy Projects Near You

Solar, wind and battery projects near Inveraray (PA32)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA32 (Argyll and Bute): 3 are waiting for a planning decision, 3 approved but not yet running, 1 operational. The largest live scheme is Loch Awe - Eredine Wind Farm (100 MW wind farm, application submitted on 20 November 2024, no decision recorded), 9.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
3awaiting a decision
3approved, not running
1operational

Projects within 10 km of PA32

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
An Suidhewind farmwind farm19.3operationalupdated Jul 2020Aug 2005granted Oct 2005Jul 2020Argyll and Bute6.3
Creag Dhubhwind farmwind farm27application submitted may be out of dateupdated Apr 2020Dec 2019—Apr 2020Argyll and Bute6.7
Ardchonnel Wind Farmwind farmwind farm45refused on appealupdated Sep 2015Dec 2013refused May 2014Sep 2015Argyll and Bute8.0
Blarghour Wind Farmwind farmwind farm84approved, not builtupdated Oct 2024May 2018granted Oct 2021Oct 2024Argyll and Bute8.7
Loch Awe - Eredine Wind Farmwind farmwind farm100application submittedupdated Dec 2024Nov 2024—Dec 2024Argyll and Bute9.0
Ladyfield Renewable Energy Parkwind farmwind farm58.5approved, not builtupdated May 2025Jan 2024granted May 2025May 2025Argyll and Bute9.7
Ladyfield Renewable Energy Parkbattery storagebattery storage41.4approved, not builtupdated May 2025Jan 2024granted May 2025May 2025Argyll and Bute9.7
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Loch Awe - Eredine Wind Farmbattery storagebattery storage—application submittedupdated Dec 2024Nov 2024—Dec 2024Argyll and Bute9.0

Distance from the average position of the PA32 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm62211270
Battery storage2110041.4

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PA32, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.