Ardchonnel Wind Farm (45 MW)

Ardchonnel Wind Farm is a 45 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 10 September 2015; the record was last updated on 15 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWwind farm
refused on appealstatus in REPD
15 September 2015record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
13 December 2013Application submitted
28 May 2014Refused by the planning authority
26 August 2014Appeal lodged
10 September 2015Appeal refused

Project details

Technology
wind farm
Capacity
45 MW
Status (REPD)
refused on appeal
Record last updated
15 September 2015
Operator or applicant
RWE
Planning authority
Argyll and Bute
Planning application reference
13/02835/PP
Appeal reference
PPA-130-2045
Turbines
15
Council area (by location)
Argyll and Bute
Time to decision
24 weeks
REPD reference
4336

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
An Suidhewind farm19.3operational3.4
Blarghour Wind Farmwind farm84approved, not built3.7
An Carr Dubh Wind Farmwind farm85.8application submitted4.4
Loch Awe - Eredine Wind Farmwind farm100application submitted5.7
Ladyfield Renewable Energy Parkbattery storage41.4approved, not built9.1
Ladyfield Renewable Energy Parkwind farm58.5approved, not built9.1
Inverlieverwind farm47.5refused9.9