Blarghour Wind Farm (84 MW)

Blarghour Wind Farm is an 84 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 October 2021, not yet built; the record was last updated on 7 October 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

84 MWwind farm
approved, not builtstatus in REPD
7 October 2024record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
14 May 2018Application submitted
29 October 2021Section 36 consent granted (Scottish Ministers)
29 October 2027Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
84 MW
Status (REPD)
approved, not built
Record last updated
7 October 2024
Operator or applicant
Coriolis Energy / ESB
Planning authority
Scottish Government (S36)
Planning application reference
EC00005267
Turbines
17 (Scottish Government ECU; REPD: 14)
Turbine height
180 m
Address (REPD)
7km north west of Inveraray and 6km east of Dalavich
Council area (by location)
Argyll and Bute
Time to decision
181 weeks
Contracts for Difference
AR5
REPD reference
6405

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ardchonnel Wind Farmwind farm45refused on appeal3.7
Ladyfield Renewable Energy Parkbattery storage41.4approved, not built5.7
Ladyfield Renewable Energy Parkwind farm58.5approved, not built5.7
An Suidhewind farm19.3operational6.6
An Carr Dubh Wind Farmwind farm85.8application submitted7.0
Upper Sonachan Wind Farmwind farm64.6refused on appeal7.2
Loch Awe - Eredine Wind Farmwind farm100application submitted9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2718, -5.1716).