Energy Projects Near You

An Suidhe (19.3 MW wind farm)

An Suidhe is a 19.3 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 4 August 2010; the record was last updated on 29 July 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.3 MWwind farm
operationalstatus in REPD
29 July 2020record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
22 August 2005Application submitted
21 October 2005Planning permission granted
1 June 2007Construction started
4 August 2010Operational

Project details

Technology
wind farm
Capacity
19.3 MW
Status (REPD)
operational
Record last updated
29 July 2020
Operator or applicant
RWE npower
Planning authority
Argyll and Bute
Planning application reference
05/01711/VARCON
Turbines
23
Address (REPD)
Dalmally, Strathclyde. PA33 On the eastern shore of Loch Awe
Council area (by location)
Argyll and Bute
Time to decision
9 weeks
REPD reference
3298

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Loch Awe - Eredine Wind Farmwind farm100application submitted3.3
Ardchonnel Wind Farmwind farm45refused on appeal3.4
An Carr Dubh Wind Farmwind farm85.8application submitted6.2
Blarghour Wind Farmwind farm84approved, not built6.6
A'Chruach (Phase 1)wind farm48.3operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2187, -5.2194).