Energy Projects Near You

A'Chruach (Phase 1) (48.3 MW wind farm)

A'Chruach (Phase 1) is a 48.3 MW wind farm project in Strathclyde, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 June 2016; the record was last updated on 4 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48.3 MWwind farm
operationalstatus in REPD
4 April 2017record last updated
Scotlandcouncil area

Planning timeline

DateStage
22 December 2011Application submitted
27 June 2012Planning permission granted
4 June 2015Construction started
29 June 2016Operational

Project details

Technology
wind farm
Capacity
48.3 MW
Status (REPD)
operational
Record last updated
4 April 2017
Operator or applicant
Infinis (formerly Novera Energy)
Planning authority
Argyll and Bute
Planning application reference
11/02520/PP
Turbines
21
Address (REPD)
Land At A'Cruach Kilmichael Forest West Of Minard Argyll
Council area (by location)
not known
Time to decision
27 weeks
REPD reference
4331

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Loch Awe - Eredine Wind Farmwind farm100application submitted6.6
An Suidhewind farm19.3operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1528, -5.3102).