An Carr Dubh Wind Farm (85.8 MW)

An Carr Dubh Wind Farm is an 85.8 MW wind farm project in Argyll and Bute, Scotland. Its status: consented by Scottish Ministers on 26 October 2026, not yet built (Scottish Government Energy Consents Unit). The Renewable Energy Planning Database (July 2026 extract) still records: application submitted on 22 March 2023, no decision recorded; the record was last updated on 10 May 2023. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

85.8 MWwind farm
approved, not builtstatus (Scottish Government Energy Consents Unit; status in REPD: application submitted)
10 May 2023record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
22 March 2023Application submitted
26 October 2026Section 36 consent granted (Scottish Ministers)

Status source: Scottish Government Energy Consents Unit. The Renewable Energy Planning Database (July 2026 extract) still shows this project as “application submitted”.

Project details

Technology
wind farm
Capacity
85.8 MW
Status
approved, not built (Scottish Government Energy Consents Unit; REPD: application submitted)
Record last updated
10 May 2023
Operator or applicant
Statkraft UK Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004781
Turbines
13
Turbine height
180 m
Address (REPD)
6km North West Of Inveraray And 4.5km East Of Dalavich
Council area (by location)
Argyll and Bute
REPD reference
13805

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ardchonnel Wind Farmwind farm45refused on appeal4.4
Inverlieverwind farm47.5refused5.7
Loch Awe - Eredine Wind Farmwind farm100application submitted6.1
An Suidhewind farm19.3operational6.2
Blarghour Wind Farmwind farm84approved, not built7.0
Carraig Ghealwind farm46operational8.6
Musdale Wind Farmwind farm64application withdrawn9.7

Status and events credited to a named source are from that source; other dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2616, -5.2835).