Inverliever (47.5 MW wind farm)

Inverliever is a 47.5 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 24 August 2005; the record was last updated on 24 November 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

47.5 MWwind farm
refusedstatus in REPD
24 November 2015record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
19 November 2002Application submitted
24 August 2005Refused by the planning authority

Project details

Technology
wind farm
Capacity
47.5 MW
Status (REPD)
refused
Record last updated
24 November 2015
Operator or applicant
Scottish Power Renewables
Planning authority
Argyll and Bute
Planning application reference
04/02070/DET
Turbines
17
Address (REPD)
Inverliever Forest Former Estate
Council area (by location)
Argyll and Bute
Time to decision
144 weeks
REPD reference
3127

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
An Carr Dubh Wind Farmwind farm85.8application submitted5.7
Loch Awe - Eredine Wind Farmwind farm100application submitted8.4
Ardchonnel Wind Farmwind farm45refused on appeal9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2544, -5.3755).