Inverliever (47.5 MW wind farm)
Inverliever is a 47.5 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 24 August 2005; the record was last updated on 24 November 2015.
47.5 MWwind farm
refusedstatus in REPD
24 November 2015record last updated
Argyll and Butecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 19 November 2002 | Application submitted |
| 24 August 2005 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 47.5 MW
- Status (REPD)
- refused
- Record last updated
- 24 November 2015
- Operator or applicant
- Scottish Power Renewables
- Planning authority
- Argyll and Bute
- Planning application reference
- 04/02070/DET
- Turbines
- 17
- Address (REPD)
- Inverliever Forest Former Estate
- Council area (by location)
- Argyll and Bute
- Time to decision
- 144 weeks
- REPD reference
- 3127
Who decides
| Applications | Argyll and Bute | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 22 (45%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 21 of 41 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 53.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| An Carr Dubh Wind Farm | wind farm | 85.8 | application submitted | 5.7 |
| Loch Awe - Eredine Wind Farm | wind farm | 100 | application submitted | 8.4 |
| Ardchonnel Wind Farm | wind farm | 45 | refused on appeal | 9.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2544, -5.3755).