Ladyfield Renewable Energy Park (41.4 MW)

Ladyfield Renewable Energy Park is a 41.4 MW battery storage project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 May 2025, not yet built; the record was last updated on 13 May 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

41.4 MWbattery storage
approved, not builtstatus in REPD
13 May 2025record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
18 January 2024Application submitted
2 May 2025Section 36 consent granted (Scottish Ministers)

Project details

Technology
battery storage (stand-alone storage)
Capacity
41.4 MW
Status (REPD)
approved, not built
Record last updated
13 May 2025
Operator or applicant
Ridge Clean Energy Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003291
Address (REPD)
Ladyfield Wind Farm, Inveraray
Council area (by location)
Argyll and Bute
Time to decision
67 weeks
REPD reference
15785

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ladyfield Renewable Energy Parkwind farm58.5approved, not built<0.1
Blarghour Wind Farmwind farm84approved, not built5.7
Upper Sonachan Wind Farmwind farm64.6refused on appeal6.5
Clachan Flats Wind Farmwind farm15operational8.5
Ardchonnel Wind Farmwind farm45refused on appeal9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2816, -5.0808).