Energy Projects Near You

Solar, wind and battery projects near Dalmally (PA33)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA33 (Argyll and Bute): 2 approved but not yet running. The largest live scheme is Ladyfield Renewable Energy Park (58.5 MW wind farm, approved on 2 May 2025, not yet built), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
0awaiting a decision
2approved, not running
0operational

Projects within 10 km of PA33

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Stacainwind farmwind farm48refused on appealupdated Feb 2013Apr 2005refused Dec 2005Feb 2013Argyll and Bute4.8
Upper Sonachan Wind Farmwind farmwind farm64.6refused on appealupdated Jun 2019Oct 2015refused May 2019Jun 2019Argyll and Bute5.6
Ladyfield Renewable Energy Parkwind farmwind farm58.5approved, not builtupdated May 2025Jan 2024granted May 2025May 2025Argyll and Bute9.5
Ladyfield Renewable Energy Parkbattery storagebattery storage41.4approved, not builtupdated May 2025Jan 2024granted May 2025May 2025Argyll and Bute9.5

Distance from the average position of the PA33 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm3010258.5
Battery storage1010041.4

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.