Energy Projects Near You

Solar, wind and battery projects near Taynuilt (PA35)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA35 (Argyll and Bute): 3 are waiting for a planning decision, 1 approved but not yet running, 2 operational. The largest live scheme is SSE Taynuilt Substation (49.9 MW battery storage, approved on 14 November 2025, not yet built), 2.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
3awaiting a decision
1approved, not running
2operational

Projects within 10 km of PA35

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Beinn Ghlas Wind Farm - Repoweringwind farmwind farm33.6application submittedupdated Oct 2025Aug 2025—Oct 2025Argyll and Bute2.2
SSE Taynuilt Substationbattery storagebattery storage49.9approved, not builtupdated Dec 2025Dec 2024granted Nov 2025Dec 2025Argyll and Bute2.4
Beinn Ghlas Wind Farmwind farmwind farm7.8operationalupdated Apr 2006May 1997granted Aug 1998Apr 2006—5.0
Cruach Clenamacrie Wind Farmwind farmwind farm45application submittedupdated Dec 2024Dec 2024—Dec 2024Argyll and Bute8.0
Cruach Clenamacrie Wind Farmbattery storagebattery storage20application submittedupdated Dec 2024Dec 2024—Dec 2024Argyll and Bute8.0
Musdale Wind Farmwind farmwind farm64application withdrawnupdated Mar 2017Aug 2013—Mar 2017—8.2
Carraig Ghealwind farmwind farm46operationalupdated Oct 2017Nov 2004granted Jun 2008Oct 2017Argyll and Bute8.3
Upper Sonachan Wind Farmwind farmwind farm64.6refused on appealupdated Jun 2019Oct 2015refused May 2019Jun 2019Argyll and Bute9.9

Distance from the average position of the PA35 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm6202178.6
Battery storage2110069.9

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.