Energy Projects Near You

SSE Taynuilt Substation (49.9 MW battery storage)

SSE Taynuilt Substation is a 49.9 MW battery storage project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 November 2025, not yet built; the record was last updated on 9 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
9 December 2025record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
6 December 2024Application submitted
14 November 2025Planning permission granted
14 November 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
9 December 2025
Operator or applicant
Downing Energy Development Company Limited
Planning authority
Argyll and Bute
Planning application reference
24/02083/PP
Address (REPD)
Adjacent To SSE Taynuilt Substation Taynuilt
Council area (by location)
Argyll and Bute
Time to decision
49 weeks
Name in REPD
SSE Taynuilt Substation - Battery Energy Storage
REPD reference
15648

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Beinn Ghlas Wind Farm - Repoweringwind farm33.6application submitted1.6
Beinn Ghlas Wind Farmwind farm7.8operational6.6
Cruach Clenamacrie Wind Farmwind farm45application submitted8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4261, -5.2265).