4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA37 (Argyll and Bute): 4 are waiting for a planning decision. The largest live scheme is Corr Chnoc Wind Farm (86.4 MW wind farm, application submitted on 4 March 2025, no decision recorded), 7.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
4awaiting a decision
0approved, not running
0operational

Projects within 10 km of PA37

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cruach Clenamacrie Wind Farmwind farmwind farm45application submittedupdated Dec 2024Dec 2024—Dec 2024Argyll and Bute6.2
Cruach Clenamacrie Wind Farmbattery storagebattery storage20application submittedupdated Dec 2024Dec 2024—Dec 2024Argyll and Bute6.2
Corr Chnoc Wind Farmwind farmwind farm86.4application submittedupdated Mar 2025Mar 2025—Mar 2025Argyll and Bute7.8
Corr Chnoc Wind Farmbattery storagebattery storage25application submittedupdated Mar 2025Mar 2025—Mar 2025Argyll and Bute7.8

Distance from the average position of the PA37 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm22000131
Battery storage2200045

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.