Energy Projects Near You

Solar, wind and battery projects near Craignure (PA65)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA65 (Argyll and Bute): 3 approved but not yet running. The largest live scheme is Rowan Wind Farm (85.8 MW wind farm, approved on 26 April 2024, not yet built), 8.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
3approved, not running
0operational

Projects within 10 km of PA65

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rowan Wind Farmwind farmwind farm85.8approved, not builtupdated Jul 2024Feb 2022granted Apr 2024Jul 2024—8.3
Glasvaar Wind Farmwind farmwind farm49.5approved, not builtupdated Jul 2026Sep 2022granted Dec 2024Jul 2026—8.3
Rowan Wind Farmbattery storagebattery storage5approved, not builtupdated Aug 2024Feb 2022granted Apr 2024Aug 2024—8.3

Distance from the average position of the PA65 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm20200135
Battery storage101005

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.