Energy Projects Near You

Rowan Wind Farm (5 MW)

Rowan Wind Farm is a 5 MW battery storage project in Strathclyde, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 April 2024, not yet built; the record was last updated on 5 August 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWbattery storage
approved, not builtstatus in REPD
5 August 2024record last updated
Scotlandcouncil area

Planning timeline

DateStage
3 February 2022Application submitted
26 April 2024Section 36 consent granted (Scottish Ministers)
26 April 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
5 August 2024
Operator or applicant
Energiekontor UK Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003230
Address (REPD)
Kilberry Wind Farm Kilberry
Council area (by location)
not known
Time to decision
116 weeks
REPD reference
16737

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Glasvaar Wind Farmwind farm49.5approved, not built<0.1
Rowan Wind Farmwind farm85.8approved, not built<0.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4603, -5.8618).