Glasvaar Wind Farm (49.5 MW)
Glasvaar Wind Farm is a 49.5 MW wind farm project in Argyll And Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 December 2024, not yet built; the record was last updated on 13 July 2026.
49.5 MWwind farm
approved, not builtstatus in REPD
13 July 2026record last updated
Scotlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 28 September 2022 | Application submitted |
| 20 December 2024 | Planning permission granted |
| 20 December 2029 | Permission due to expire (unless work starts) |
Project details
- Technology
- wind farm
- Capacity
- 49.5 MW
- Status (REPD)
- approved, not built
- Record last updated
- 13 July 2026
- Operator or applicant
- E Power Limited
- Planning authority
- Argyll and Bute
- Planning application reference
- 22/01380/PP
- Turbines
- 11
- Turbine height
- 150 m
- Address (REPD)
- Sidh Mor S/o Lochan Anama & Nw/o A-Chruach Wind Farm, Kilmichael Forest,
- Council area (by location)
- not known
- Time to decision
- 116 weeks
- REPD reference
- 9662
Who decides
| Applications | Argyll and Bute | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 22 (45%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 21 of 41 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 53.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Rowan Wind Farm | wind farm | 85.8 | approved, not built | <0.1 |
| Rowan Wind Farm | battery storage | 5 | approved, not built | <0.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4603, -5.8618).