Corr Chnoc Wind Farm (86.4 MW)
Corr Chnoc Wind Farm is an 86.4 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 4 March 2025, no decision recorded; the record was last updated on 7 March 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.
Planning timeline
| Date | Stage |
|---|---|
| 4 March 2025 | Application submitted |
Project details
- Technology
- wind farm
- Capacity
- 86.4 MW
- Status (REPD)
- application submitted
- Record last updated
- 7 March 2025
- Operator or applicant
- Galileo Green Energy Scotland Limited
- Planning authority
- Scottish Government (S36)
- Planning application reference
- ECU00006023
- Turbines
- 12
- Turbine height
- 200 m
- Address (REPD)
- Approximately 2km NE/O The Village Of Kilmore, 5km E/O The Centre Of Oban, Oban
- Council area (by location)
- Argyll and Bute
- REPD reference
- 14299
The scheme also includes 25 MW of battery storage, recorded separately in REPD (application submitted).
Who decides
As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Tullich Wind Farm | wind farm | 180 | application withdrawn | 3.0 |
| Cruach Clenamacrie Wind Farm | wind farm | 45 | application submitted | 7.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.412, -5.4726).