Corr Chnoc Wind Farm (86.4 MW)

Corr Chnoc Wind Farm is an 86.4 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 4 March 2025, no decision recorded; the record was last updated on 7 March 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

86.4 MWwind farm
application submittedstatus in REPD
7 March 2025record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
4 March 2025Application submitted

Project details

Technology
wind farm
Capacity
86.4 MW
Status (REPD)
application submitted
Record last updated
7 March 2025
Operator or applicant
Galileo Green Energy Scotland Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00006023
Turbines
12
Turbine height
200 m
Address (REPD)
Approximately 2km NE/O The Village Of Kilmore, 5km E/O The Centre Of Oban, Oban
Council area (by location)
Argyll and Bute
REPD reference
14299

The scheme also includes 25 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Tullich Wind Farmwind farm180application withdrawn3.0
Cruach Clenamacrie Wind Farmwind farm45application submitted7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.412, -5.4726).