Stacain (48 MW wind farm)

Stacain is a 48 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 15 October 2009; the record was last updated on 27 February 2013. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWwind farm
refused on appealstatus in REPD
27 February 2013record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
1 April 2005Application submitted
10 December 2005Refused by the planning authority
15 October 2009Appeal refused

Project details

Technology
wind farm
Capacity
48 MW
Status (REPD)
refused on appeal
Record last updated
27 February 2013
Operator or applicant
Wind Prospect
Planning authority
Scottish Government (S36)
Planning application reference
05/00770/DET
Turbines
14
Address (REPD)
Near Inverary, to the north-east of Sròn Mór hydroelectric station, near Lochan Shira.
Council area (by location)
Argyll and Bute
Time to decision
36 weeks
REPD reference
4049

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Clachan Flats Wind Farmwind farm15operational8.3
Upper Sonachan Wind Farmwind farm64.6refused on appeal9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3587, -4.988).