Energy Projects Near You

Clachan Flats Wind Farm (15 MW)

Clachan Flats Wind Farm is a 15 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2008; the record was last updated on 27 July 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
operationalstatus in REPD
27 July 2010record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
15 May 2002Application submitted
8 July 2004Planning permission granted
1 May 2006Construction started
1 December 2008Operational

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
27 July 2010
Operator or applicant
AMEC/ Border Winds
Planning authority
Argyll and Bute
Planning application reference
02/00/953/DET
Turbines
9
Address (REPD)
North of the head of Loch Fyne Ardkinlas
Council area (by location)
Argyll and Bute
Time to decision
112 weeks
REPD reference
3448

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stacainwind farm48refused on appeal8.3
Ladyfield Renewable Energy Parkbattery storage41.4approved, not built8.5
Ladyfield Renewable Energy Parkwind farm58.5approved, not built8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2881, -4.9429).