Energy Projects Near You

Solar, wind and battery projects near Cairndow (PA26)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA26 (Argyll and Bute): 1 is waiting for a planning decision, 2 approved but not yet running, 1 operational. The largest live scheme is Ladyfield Renewable Energy Park (58.5 MW wind farm, approved on 2 May 2025, not yet built), 9.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
1awaiting a decision
2approved, not running
1operational

Projects within 10 km of PA26

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Clachan Flats Wind Farmwind farmwind farm15operationalupdated Jul 2010May 2002granted Jul 2004Jul 2010Argyll and Bute3.2
Ladyfield Renewable Energy Parkwind farmwind farm58.5approved, not builtupdated May 2025Jan 2024granted May 2025May 2025Argyll and Bute9.3
Ladyfield Renewable Energy Parkbattery storagebattery storage41.4approved, not builtupdated May 2025Jan 2024granted May 2025May 2025Argyll and Bute9.3
Creag Dhubhwind farmwind farm27application submitted may be out of dateupdated Apr 2020Dec 2019—Apr 2020Argyll and Bute9.4

Distance from the average position of the PA26 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm3111085.5
Battery storage1010041.4

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PA26, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.