Solar, wind and battery projects near Collintraive (PA22)
4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA22 (Argyll and Bute): 1 operational. The largest scheme is Black Craig (47.5 MW wind farm, application withdrawn on 1 December 2009), 7.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PA22
Projects of 1 MW and more (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Stronafian Community Forest Wind Turbineswind farm | wind farm | 1.6 | refusedupdated Sep 2016 | Jul 2015 | refused Aug 2016 | Sep 2016 | Argyll and Bute | 5.3 |
| Ardtaraig Wind Farmwind farm | wind farm | 29.4 | refused on appealupdated Dec 2019 | Aug 2018 | refused Mar 2019 | Dec 2019 | Argyll and Bute | 6.0 |
| Cruach Mhorwind farm | wind farm | 33.3 | operationalupdated Jul 2004 | Sep 2001 | granted Jun 2002 | Jul 2004 | Argyll and Bute | 7.6 |
| Black Craigwind farm | wind farm | 47.5 | application withdrawnupdated Dec 2009 | — | — | Dec 2009 | Argyll and Bute | 7.7 |
Distance from the average position of the PA22 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Wind farm | 4 | 0 | 0 | 1 | 2 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Argyll and Bute decides solar, wind and battery applications
| Applications | Argyll and Bute | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 22 (45%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 21 of 41 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 53.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 4 | — |
All projects in Argyll and Bute
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.