Energy Projects Near You

Cruach Mhor (33.3 MW wind farm)

Cruach Mhor is a 33.3 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 January 2004; the record was last updated on 27 July 2004.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

33.3 MWwind farm
operationalstatus in REPD
27 July 2004record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
18 September 2001Application submitted
6 June 2002Planning permission granted
31 January 2004Operational

Project details

Technology
wind farm
Capacity
33.3 MW
Status (REPD)
operational
Record last updated
27 July 2004
Operator or applicant
Scottish Power Renewables
Planning authority
Argyll and Bute
Planning application reference
01/01553/DET
Turbines
35
Address (REPD)
Cruach Mhor, Cowal, Glen Dareul, Agyll, Bute
Council area (by location)
Argyll and Bute
Time to decision
37 weeks
REPD reference
3585

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ardtaraig Wind Farmwind farm29.4refused on appeal1.6
Strone Saul Hillwind farm20refused9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.039, -5.1559).