Ardtaraig Wind Farm (29.4 MW)

Ardtaraig Wind Farm is a 29.4 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 7 November 2019; the record was last updated on 17 December 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.4 MWwind farm
refused on appealstatus in REPD
17 December 2019record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
3 August 2018Application submitted
29 March 2019Refused by the planning authority
26 June 2019Appeal lodged
7 November 2019Appeal refused

Project details

Technology
wind farm
Capacity
29.4 MW
Status (REPD)
refused on appeal
Record last updated
17 December 2019
Operator or applicant
Boralex/Infinergy
Planning authority
Argyll and Bute
Planning application reference
18/01516/PP
Appeal reference
PPA-130-2073
Turbines
7
Turbine height
137 m
Address (REPD)
Located around 14.5km to the west of Dunoon, near Loch Striven, adjacent to the Stronafian Community Forest, Strathclyde
Council area (by location)
Argyll and Bute
Time to decision
34 weeks
REPD reference
6336

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cruach Mhorwind farm33.3operational1.6
Strone Saul Hillwind farm20refused9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0247, -5.1516).