Solar, wind and battery projects near Dunoon (PA23)
13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA23 (Argyll and Bute): 3 are waiting for a planning decision, 4 approved but not yet running. The largest live scheme is Giants Burn Wind Farm- (50.4 MW wind farm, application submitted on 15 July 2025, no decision recorded), 2.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PA23
Projects of 1 MW and more (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Giants Burn Wind Farm-wind farm | wind farm | 50.4 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 | Argyll and Bute | 2.8 |
| Giants Burn Wind Farm -Batter Energy Storagebattery storage | battery storage | 23 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 | Argyll and Bute | 2.8 |
| Corlarach Hillwind farm | wind farm | 42 | refused on appealupdated Dec 2010 | Jun 2007 | refused Jan 2008 | Dec 2010 | Argyll and Bute | 4.4 |
| Black Craigwind farm | wind farm | 47.5 | application withdrawnupdated Dec 2009 | — | — | Dec 2009 | Argyll and Bute | 5.5 |
| Kip Water Hydro Schemebattery storage | battery storage | 1 | application submitted may be out of dateupdated Dec 2018 | Oct 2018 | — | Dec 2018 | Inverclyde | 6.3 |
| Flatterton Farm, Flatterton Roadbattery storage | battery storage | 49.9 | approved, not builtupdated Jun 2024 | Oct 2023 | granted Jun 2024 | Jun 2024 | Inverclyde | 6.4 |
| Berfern Farmbattery storage | battery storage | 5 | permission expiredupdated Jul 2020 | May 2018 | — | Jul 2020 | Inverclyde | 7.1 |
| Leapmoor Forestwind farm | wind farm | 30 | application withdrawnupdated Mar 2011 | Jul 2006 | — | Mar 2011 | Inverclyde | 8.8 |
| Strone Saul Hillwind farm | wind farm | 20 | refusedupdated Apr 2011 | Apr 2009 | refused Aug 2010 | Apr 2011 | Argyll and Bute | 9.1 |
| Cove Community Wind Farmwind farm | wind farm | 11.5 | application withdrawnupdated Aug 2013 | Dec 2012 | — | Aug 2013 | Argyll and Bute | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (3)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Ardnadam Electricity Sub Station, Sandbankbattery storage | battery storage | — | approved, not built may be out of dateupdated Feb 2025 | Sep 2022 | granted May 2023 | Feb 2025 | Argyll and Bute | 2.7 |
| Faulds Park Road- Solar PV Panlelsrooftop solar | rooftop solar | 0.3 | under constructionupdated Apr 2022 | Apr 2022 | granted Jul 2022 | Apr 2022 | Inverclyde | 4.6 |
| Greenock Headworks, Eldon Streetrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2023 | Oct 2022 | granted Dec 2022 | Jan 2023 | Inverclyde | 8.4 |
Distance from the average position of the PA23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Rooftop solar | 2 | 0 | 2 | 0 | 0 | 0.6 |
| Wind farm | 6 | 1 | 0 | 0 | 2 | 50.4 |
| Battery storage | 5 | 2 | 2 | 0 | 0 | 73.9 |
MW in pipeline: pending, approved and under-construction capacity.
How Argyll and Bute decides solar, wind and battery applications
| Applications | Argyll and Bute | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 22 (45%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 21 of 41 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 53.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 4 | — |
All projects in Argyll and Bute
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PA23, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.