Corlarach Hill (42 MW wind farm)

Corlarach Hill is a 42 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 27 May 2009; the record was last updated on 7 December 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42 MWwind farm
refused on appealstatus in REPD
7 December 2010record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
1 June 2007Application submitted
29 January 2008Refused by the planning authority
27 May 2009Appeal refused

Project details

Technology
wind farm
Capacity
42 MW
Status (REPD)
refused on appeal
Record last updated
7 December 2010
Operator or applicant
West Coast Energy
Planning authority
Argyll and Bute
Planning application reference
07/00851/DET
Turbines
16
Address (REPD)
Corlarach Hill Argyll and Bute
Council area (by location)
Argyll and Bute
Time to decision
35 weeks
REPD reference
3010

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Black Craigwind farm47.5application withdrawn2.8
Giants Burn Wind Farm -Batter Energy Storagebattery storage23application submitted6.6
Giants Burn Wind Farm-wind farm50.4application submitted6.6
Berfern Farmbattery storage5permission expired7.7
Flatterton Farm, Flatterton Roadbattery storage49.9approved, not built9.2
Leapmoor Forestwind farm30application withdrawn9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9273, -4.9867).