Energy Projects Near You

Solar, wind and battery projects near Tarbert (PA29)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA29 (Argyll and Bute): 1 is waiting for a planning decision, 1 approved but not yet running, 1 operational. The largest live scheme is Earraghail Renewable Energy Development (78 MW wind farm, application submitted on 21 February 2022, no decision recorded; REPD status may be out of date), 6.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
1awaiting a decision
1approved, not running
1operational

Projects within 10 km of PA29

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Freasdail Wind Farmwind farmwind farm22.5operationalupdated May 2017Oct 2012granted Apr 2014May 2017Argyll and Bute3.3
Gartnagrenachwind farmwind farm24application withdrawnupdated Apr 2006——Apr 2006Argyll and Bute3.8
Sheirdrim Renewable Energy Development Windwind farmwind farm114refused on appealupdated Jun 2023Oct 2019—Jun 2023Argyll and Bute4.8
Sheirdrim Renewable Energy Development Batterybattery storagebattery storage38refused on appealupdated Jul 2023Oct 2019—Jul 2023Argyll and Bute4.8
Sheirdrim Renewable Energy Development Solarsolar farmsolar farm20refused on appealupdated Jun 2023Oct 2019—Jun 2023Argyll and Bute4.8
Earraghail Renewable Energy Developmentwind farmwind farm78application submitted may be out of dateupdated Mar 2023Feb 2022—Mar 2023—6.2
Earraghail Renewable Energy Developmentbattery storagebattery storage25refusedupdated Apr 2025Feb 2022refused Feb 2025Apr 2025Argyll and Bute6.3
Earraghail Renewable Energy Developmentsolar farmsolar farm5refusedupdated Apr 2025Feb 2022refused Feb 2025Apr 2025Argyll and Bute7.0
Airigh Wind Farmwind farmwind farm58.8abandonedupdated May 2024Sep 2017granted Mar 2020May 2024—7.5
Eascairt Wind Farmwind farmwind farm26approved, not builtupdated May 2020Feb 2015granted Sep 2018May 2020Argyll and Bute7.6

Distance from the average position of the PA29 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200020
Wind farm61111104
Battery storage200020

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PA29, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.