Energy Projects Near You

Solar, wind and battery projects near Ardminish (PA41)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA41 (Argyll and Bute): 1 is waiting for a planning decision, 2 approved but not yet running. The largest live scheme is Clachaig Glen (60 MW wind farm, approved on 5 November 2024, not yet built), 9.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
1awaiting a decision
2approved, not running
0operational

Projects within 10 km of PA41

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Killean Wind Farmwind farmwind farm59.4application submittedupdated Oct 2024Aug 2024—Oct 2024Argyll and Bute8.3
Largie Windfarm IIwind farmwind farm21refusedupdated Apr 2007Aug 2004refused Mar 2007Apr 2007Argyll and Bute9.2
Clachaig Glenwind farmwind farm60approved, not builtupdated Feb 2026Mar 2022granted Nov 2024Feb 2026Argyll and Bute9.6
Clachaig Glenbattery storagebattery storage30approved, not builtupdated Dec 2024Mar 2022granted Nov 2024Dec 2024Argyll and Bute9.6
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Gigha Wind Farm Battery Projectbattery storagebattery storage0.1decommissionedupdated Jul 2017——Jul 2017Argyll and Bute1.2

Distance from the average position of the PA41 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm31101119
Battery storage2010030

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.