Energy Projects Near You

Solar, wind and battery projects near Campbeltown (PA28)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA28 (Argyll and Bute): 2 are waiting for a planning decision, 1 approved but not yet running, 2 operational. The largest live scheme is Cnoc Buidhe Windfarm (191 MW wind farm, application submitted on 10 April 2025, no decision recorded), 1.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
2awaiting a decision
1approved, not running
2operational

Projects within 10 km of PA28

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cnoc Buidhe Windfarmwind farmwind farm191application submittedupdated Apr 2025Apr 2025—Apr 2025Argyll and Bute1.5
Cnoc Buidhe Windfarmbattery storagebattery storage109application submittedupdated Apr 2025Apr 2025—Apr 2025Argyll and Bute1.5
Tangy Wind Farm Extension/Tangy 2wind farmwind farm6operationalupdated Jan 2012Jul 2004granted Sep 2005Jan 2012Argyll and Bute6.5
Tangy Farm Wind Turbinewind turbinewind turbine2application withdrawnupdated Dec 2014Nov 2012—Dec 2014Argyll and Bute7.3
Tangy 4 Wind Farmwind farmwind farm80approved, not built may be out of dateupdated Aug 2025Sep 2018granted Dec 2019Aug 2025Argyll and Bute7.6
Tangy Wind Farm - repowering/Tangy 3wind farmwind farm36.8permission expiredupdated Oct 2018Dec 2014granted Jun 2015Oct 2018Argyll and Bute7.6
Tangy Wind Farm/Tangy 1wind farmwind farm12.8operationalupdated Jan 2012Jun 2001granted Feb 2002Jan 2012Argyll and Bute7.6
Low Ugadale Farmwind farmwind farm1.5application withdrawnupdated Mar 2014Oct 2013—Mar 2014Argyll and Bute8.8
Kilchattanwind farmwind farm13.6refused on appealupdated Mar 2012Jan 2008refused Mar 2011Mar 2012Argyll and Bute9.9

Distance from the average position of the PA28 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm71121271
Wind turbine100000
Battery storage11000109

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PA28, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.