Tangy Wind Farm - repowering/Tangy 3 (36.8 MW)

Tangy Wind Farm - repowering/Tangy 3 is a 36.8 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 29 June 2018; the record was last updated on 3 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36.8 MWwind farm
permission expiredstatus in REPD
3 October 2018record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
11 December 2014Application submitted
29 June 2015Planning permission granted
29 June 2018Permission expired

Project details

Technology
wind farm
Capacity
36.8 MW
Status (REPD)
permission expired
Record last updated
3 October 2018
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Argyll and Bute
Planning application reference
14/02969/PP
Turbines
15 (SSE; REPD: 16)
Turbine height
125 m
Address (REPD)
Tangy, Kilkenzie, Campbeltown, Argyll And Bute
Council area (by location)
Argyll and Bute
Time to decision
29 weeks
REPD reference
4277

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tangy Wind Farm/Tangy 1wind farm12.8operational<0.1
Tangy 4 Wind Farmwind farm80approved, not built<0.1
Auchadaduie Wind Farmwind farm6.9operational5.5
Beinn an Tuirc Windfarm Phase 3wind farm49.9under construction6.6
Blary Hill Wind Farmwind farm35operational8.2
Creggan Wind Farmwind farm54refused on appeal8.5
Tangy Wind Farm Extension/Tangy 2wind farm6operational8.8
Cnoc Buidhe Windfarmwind farm191application submitted8.8
Wind Turbines at Allt Domhain Wind Farmwind farm64.8application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4953, -5.6666).