Energy Projects Near You

Beinn an Tuirc Windfarm Phase 3 (49.9 MW)

Beinn an Tuirc Windfarm Phase 3 is a 49.9 MW wind farm project in Argyll and Bute, Scotland. Its status: operational since October 2021 (ScottishPower). The Renewable Energy Planning Database (July 2026 extract) still records: under construction since 1 February 2020; the record was last updated on 28 May 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWwind farm
operationalstatus (ScottishPower; status in REPD: under construction)
28 May 2020record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
3 November 2015Application submitted
23 February 2017Planning permission granted
1 February 2020Construction started
28 October 2021Operational (ScottishPower)

Status source: ScottishPower. The Renewable Energy Planning Database (July 2026 extract) still shows this project as “under construction”.

Project details

Technology
wind farm
Capacity
49.9 MW
Status
operational (ScottishPower; REPD: under construction)
Record last updated
28 May 2020
Operator or applicant
Scottish Power Renewables
Planning authority
Argyll and Bute
Planning application reference
15/03057/PP
Turbines
19
Address (REPD)
Beinn An Tuirc Windfarm, Land At Meall Buidhe And South, A Chruach West Of Saddell Kin, Campbeltown, Strathclyde, Scotland
Council area (by location)
Argyll and Bute
Time to decision
68 weeks
REPD reference
3387

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Auchadaduie Wind Farmwind farm6.9operational3.1
Blary Hill Wind Farmwind farm35operational3.2
Beinn an Tuircwind farm29.7operational3.4
Beinn an Tuirc Phase 2wind farm43.7operational3.4
Cnoc Donn Arniclewind farm15operational4.7
Largie Wind Farmwind farm14.9refused5.1
Wind Turbines at Allt Domhain Wind Farmwind farm64.8application submitted6.3
Creggan Wind Farmwind farm54refused on appeal6.4
Tangy Wind Farm/Tangy 1wind farm12.8operational6.6

Status and events credited to a named source are from that source; other dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5457, -5.6115).