Cnoc Donn Arnicle (15 MW wind farm)

Cnoc Donn Arnicle is a 15 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2001; the record was last updated on 3 February 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
operationalstatus in REPD
3 February 2010record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
20 April 1998Application submitted
28 April 1999Planning permission granted
1 October 2001Operational

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
3 February 2010
Operator or applicant
CRE Energy/ Scottish Power
Planning authority
Argyll and Bute
Planning application reference
not recorded
Turbines
26
Address (REPD)
Situated next to Beinn an Tuirc Kintyre
Council area (by location)
Argyll and Bute
Time to decision
53 weeks
REPD reference
3294

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Beinn an Tuirc Phase 2wind farm43.7operational1.4
Beinn an Tuircwind farm29.7operational1.4
Largie Wind Farmwind farm14.9refused2.6
West Torrisdale Wind Farmwind farm54application submitted4.4
Beinn an Tuirc Windfarm Phase 3wind farm49.9under construction4.7
Blary Hill Wind Farmwind farm35operational4.9
Clachaig Glenwind farm60approved, not built5.6
Deucheran Hillwind farm15.8operational5.7
Auchadaduie Wind Farmwind farm6.9operational7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.58, -5.5681).