West Torrisdale Wind Farm (54 MW)

West Torrisdale Wind Farm is a 54 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 6 January 2025, no decision recorded; the record was last updated on 7 April 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

54 MWwind farm
application submittedstatus in REPD
7 April 2025record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
6 January 2025Application submitted

Project details

Technology
wind farm
Capacity
54 MW
Status (REPD)
application submitted
Record last updated
7 April 2025
Operator or applicant
ESB Asset Development UK
Planning authority
Scottish Government (S36)
Planning application reference
ECU00002224
Turbines
9
Turbine height
150 m
Address (REPD)
West Torrisdale Wind Farm Approx 4km South West Of Carradale Kintyre Argyll And Bute
Council area (by location)
Argyll and Bute
REPD reference
8490

The scheme also includes 20 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Cnoc Donn Arniclewind farm15operational4.4
Beinn an Tuircwind farm29.7operational5.4
Beinn an Tuirc Phase 2wind farm43.7operational5.4
Largie Wind Farmwind farm14.9refused6.9
Deucheran Hillwind farm15.8operational7.2
Beinn an Tuirc Windfarm Phase 3wind farm49.9under construction7.4
Blary Hill Wind Farmwind farm35operational8.9
Clachaig Glenwind farm60approved, not built9.6