Clachaig Glen (60 MW wind farm)

Clachaig Glen is a 60 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 November 2024, not yet built; the record was last updated on 10 February 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWwind farm
approved, not builtstatus in REPD
10 February 2026record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
17 March 2022Application submitted
5 November 2024Section 36 consent granted (Scottish Ministers)
5 November 2029Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
60 MW
Status (REPD)
approved, not built
Record last updated
10 February 2026
Operator or applicant
RWE UK
Planning authority
Scottish Government (S36)
Planning application reference
ECU00002103
Turbines
12
Turbine height
200 m
Address (REPD)
Kintyre Peninsula, approximately 20km north of Campbeltown and 1.8km north east of Muasdale
Council area (by location)
Argyll and Bute
Time to decision
138 weeks
Contracts for Difference
AR7a
REPD reference
8000

The scheme also includes 30 MW of battery storage, recorded separately in REPD (approved, not built).

Earlier applications for this site

ApplicationMWSubmittedOutcome
Bridge House, Muasdale, Tarbert, Strathclyde 16/01313/PP47.618 May 2016refused 21 September 2017
Clachaig Glen ECU000021036017 March 2022approved on 5 November 2024, not yet built

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Killean Wind Farmwind farm59.4application submitted3.3
Largie Wind Farmwind farm14.9refused3.3
Deucheran Hillwind farm15.8operational5.3
Beinn an Tuirc Phase 2wind farm43.7operational5.6
Beinn an Tuircwind farm29.7operational5.6
Cnoc Donn Arniclewind farm15operational5.6
Blary Hill Wind Farmwind farm35operational5.7
Wind Turbines at Allt Domhain Wind Farmwind farm64.8application submitted6.0
Narachan Wind Farmwind farm72.6refused6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6189, -5.6259).