Energy Projects Near You

Deucheran Hill (15.8 MW wind farm)

Deucheran Hill is a 15.8 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 November 2001; the record was last updated on 5 August 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15.8 MWwind farm
operationalstatus in REPD
5 August 2019record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
1 June 1999Application submitted
22 May 2001Planning permission granted
30 November 2001Operational

Project details

Technology
wind farm
Capacity
15.8 MW
Status (REPD)
operational
Record last updated
5 August 2019
Operator or applicant
Powergen Renewables
Planning authority
Argyll and Bute
Planning application reference
99/00925/DET
Turbines
9
Address (REPD)
Deucheran Hill Nr. Muasdale
Council area (by location)
Argyll and Bute
Time to decision
103 weeks
REPD reference
3554

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Narachan Wind Farmwind farm72.6refused4.7
Killean Wind Farmwind farm59.4application submitted5.2
Clachaig Glenwind farm60approved, not built5.3
Largie Wind Farmwind farm14.9refused5.6
Cnoc Donn Arniclewind farm15operational5.7
Beinn an Tuirc Phase 2wind farm43.7operational6.8
Beinn an Tuircwind farm29.7operational6.8
Cour Wind Farmwind farm20.5operational6.8
West Torrisdale Wind Farmwind farm54application submitted7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6293, -5.544).