Auchadaduie Wind Farm (6.9 MW)
Auchadaduie Wind Farm is a 6.9 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 21 November 2018; the record was last updated on 26 November 2018.
6.9 MWwind farm
operationalstatus in REPD
26 November 2018record last updated
Argyll and Butecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 18 January 2012 | Application submitted |
| 21 July 2014 | Planning permission granted |
| 15 January 2018 | Construction started |
| 21 November 2018 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 6.9 MW
- Status (REPD)
- operational
- Record last updated
- 26 November 2018
- Operator or applicant
- Fyne Futures
- Planning authority
- Argyll and Bute
- Planning application reference
- 11/02525/PP
- Turbines
- 3
- Address (REPD)
- Land South Of Auchadaduie Barr Glen Glenbarr Kintyre
- Council area (by location)
- Argyll and Bute
- Time to decision
- 131 weeks
- REPD reference
- 4184
Who decides
| Applications | Argyll and Bute | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 22 (45%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 21 of 41 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 53.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Blary Hill Wind Farm | wind farm | 35 | operational | 2.8 |
| Beinn an Tuirc Windfarm Phase 3 | wind farm | 49.9 | under construction | 3.1 |
| Creggan Wind Farm | wind farm | 54 | refused on appeal | 3.9 |
| Wind Turbines at Allt Domhain Wind Farm | wind farm | 64.8 | application submitted | 4.4 |
| Tangy Wind Farm/Tangy 1 | wind farm | 12.8 | operational | 5.5 |
| Tangy 4 Wind Farm | wind farm | 80 | approved, not built | 5.5 |
| Tangy Wind Farm - repowering/Tangy 3 | wind farm | 36.8 | permission expired | 5.5 |
| Beinn an Tuirc | wind farm | 29.7 | operational | 5.6 |
| Beinn an Tuirc Phase 2 | wind farm | 43.7 | operational | 5.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5447, -5.6602).