Energy Projects Near You

Tangy 4 Wind Farm (80 MW)

Tangy 4 Wind Farm is an 80 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 December 2019, not yet built; the record was last updated on 11 August 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. REPD also records that the planning permission expired on 20 December 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

80 MWwind farm
approved, not builtmay be out of datestatus in REPD
11 August 2025record last updated
Argyll and Butecouncil area

REPD also records that the planning permission expired on 20 December 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
6 September 2018Application submitted
20 December 2019Section 36 consent granted (Scottish Ministers)
20 December 2024Permission expired

Project details

Technology
wind farm
Capacity
80 MW
Status (REPD)
approved, not built
Record last updated
11 August 2025
Operator or applicant
Scottish & Southern (SSE)
Planning authority
Scottish Government (S36)
Planning application reference
ECU00000673
Turbines
16
Turbine height
150 m
Address (REPD)
Tangy, Kilkenzie, Campbeltown, Argyll And Bute
Council area (by location)
Argyll and Bute
Time to decision
67 weeks
REPD reference
6734

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Tangy Wind Farm/Tangy 1wind farm12.8operational<0.1
Tangy Wind Farm - repowering/Tangy 3wind farm36.8permission expired<0.1
Auchadaduie Wind Farmwind farm6.9operational5.5
Beinn an Tuirc Windfarm Phase 3wind farm49.9under construction6.6
Blary Hill Wind Farmwind farm35operational8.2
Creggan Wind Farmwind farm54refused on appeal8.5
Tangy Wind Farm Extension/Tangy 2wind farm6operational8.8
Cnoc Buidhe Windfarmwind farm191application submitted8.8
Wind Turbines at Allt Domhain Wind Farmwind farm64.8application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4953, -5.6666).