Solar, wind and battery projects near Brodick (KA27)
1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of KA27 (North Ayrshire): 1 approved but not yet running. The largest live scheme is Glenkiln Farm, Lamlash Brodick Solar Farm (6 MW solar farm, approved on 20 March 2025, not yet built), 2.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of KA27
Projects of 1 MW and more (1)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Glenkiln Farm, Lamlash Brodick Solar Farmsolar farm | solar farm | 6 | approved, not builtupdated Nov 2025 | Jan 2025 | granted Mar 2025 | Nov 2025 | North Ayrshire | 2.0 |
Distance from the average position of the KA27 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 1 | 0 | 1 | 0 | 0 | 6 |
MW in pipeline: pending, approved and under-construction capacity.
How North Ayrshire decides solar, wind and battery applications
| Applications | North Ayrshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 12 (26%) | 19% |
| Solar refused | 1 of 18 | 12% |
| Onshore wind refused | 10 of 21 | 45% |
| Battery storage refused | 1 of 8 | 16% |
| Median time from submission to decision | 24.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 5 | — |
All projects in North Ayrshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.