Solar, wind and battery projects near West Kilbride (KA23)
28 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KA23 (North Ayrshire): 2 are waiting for a planning decision, 9 approved but not yet running, 7 operational. The largest live scheme is Hunterston Grid Services Complex Energy Storage Facility (400 MW battery storage, approved on 5 January 2022, not yet built), 3.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of KA23
Projects of 1 MW and more (26)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Blackshaw Community Wind Farmwind farm | wind farm | 21 | refused on appealupdated Aug 2016 | Apr 2015 | refused Nov 2015 | Aug 2016 | North Ayrshire | 2.4 |
| Land at Hunterston Estatesolar farm | solar farm | 5 | abandonedupdated Jan 2019 | Nov 2015 | granted Jan 2016 | Jan 2019 | North Ayrshire | 2.7 |
| Hunterston Grid Services Complex Energy Storage Facilitybattery storage | battery storage | 400 | approved, not builtupdated Feb 2022 | Aug 2021 | granted Jan 2022 | Feb 2022 | North Ayrshire | 3.1 |
| Crosbie Wind Farmwind farm | wind farm | 98 | application submittedupdated Apr 2025 | Jan 2025 | — | Apr 2025 | North Ayrshire | 4.6 |
| Crosbie Wind Farmbattery storage | battery storage | 50 | application submittedupdated Apr 2025 | Jan 2025 | — | Apr 2025 | North Ayrshire | 4.7 |
| Hunterston Test Centre (Phase 2)wind turbine | wind turbine | 8 | application withdrawnupdated Sep 2016 | Jan 2016 | — | Sep 2016 | North Ayrshire | 4.8 |
| High Boydstone Farmbattery storage | battery storage | 100 | approved, not builtupdated Jul 2025 | Oct 2024 | granted Jun 2025 | Jul 2025 | North Ayrshire | 4.9 |
| Hunterston Test Centrewind farm | wind farm | 13 | decommissionedupdated Nov 2019 | Sep 2011 | granted Feb 2012 | Nov 2019 | North Ayrshire | 5.1 |
| Wardlaw Woodwind farm | wind farm | 18 | operationalupdated Oct 2009 | Dec 2002 | granted Sep 2003 | Oct 2009 | North Ayrshire | 5.4 |
| Sorbie Farmwind farm | wind farm | 9 | under constructionupdated Dec 2021 | Oct 2013 | granted Jun 2014 | Dec 2021 | North Ayrshire | 5.4 |
| Sorbie Farm wind clusterwind farm | wind farm | 7.5 | application withdrawnupdated Jul 2013 | May 2013 | — | Jul 2013 | North Ayrshire | 5.4 |
| Meiklelaught Farmbattery storage | battery storage | 30 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | North Ayrshire | 6.3 |
| Ardrossanwind farm | wind farm | 24 | operationalupdated Aug 2004 | May 2002 | granted Jan 2003 | Aug 2004 | North Ayrshire | 6.4 |
| Ardrossan Extensionwind farm | wind farm | 6 | operationalupdated Jan 2012 | Dec 2005 | granted Nov 2007 | Jan 2012 | North Ayrshire | 6.4 |
| Millour Hill Community Windfarmwind farm | wind farm | 18 | operationalupdated Mar 2015 | Jun 2009 | granted Dec 2009 | Mar 2015 | North Ayrshire | 6.6 |
| Millour Hill Community Windfarm (Extension)wind farm | wind farm | 6.4 | operationalupdated Apr 2017 | Nov 2013 | granted Jun 2014 | Apr 2017 | North Ayrshire | 6.7 |
| Hunterstonewind farm | wind farm | 30 | refusedupdated Nov 2015 | Jan 2003 | refused Dec 2003 | Nov 2015 | North Ayrshire | 7.1 |
| Auld Claywind farm | wind farm | 9.2 | refusedupdated Oct 2015 | Apr 2015 | refused Sep 2015 | Oct 2015 | North Ayrshire | 7.3 |
| Wardlaw Wood Windfarmbattery storage | battery storage | 20 | approved, not builtupdated Sep 2023 | Aug 2023 | granted Sep 2023 | Sep 2023 | North Ayrshire | 7.3 |
| Wardlaw Wood Solar Farmsolar farm | solar farm | 20 | approved, not builtupdated Nov 2024 | Oct 2024 | granted Nov 2024 | Nov 2024 | North Ayrshire | 7.3 |
| Kelburnwind farm | wind farm | 28 | operationalupdated May 2012 | Jul 2004 | granted Aug 2009 | May 2012 | North Ayrshire | 7.7 |
| Site To North East Of, Lochcraigs Farmsolar farm | solar farm | 5 | operationalupdated Nov 2016 | May 2015 | granted Aug 2015 | Nov 2016 | North Ayrshire | 8.2 |
| Ardeerwind farm | wind farm | 22 | application withdrawnupdated Aug 2004 | — | — | Aug 2004 | North Ayrshire | 9.0 |
| Castlehill Solar Farmsolar farm | solar farm | 5 | abandonedupdated May 2016 | Aug 2015 | granted Oct 2015 | May 2016 | North Ayrshire | 9.2 |
| Toftsbattery storage | battery storage | 19.9 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | North Ayrshire | 9.3 |
| Ballochmartin Farm Turbinewind turbine | wind turbine | 2.3 | application withdrawnupdated Aug 2011 | Jun 2011 | — | Aug 2011 | North Ayrshire | 9.4 |
Smaller schemes under 1 MW, mostly rooftop solar (2)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Stevenston Sewage Treatment Workssolar farm | solar farm | 0.6 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Apr 2025 | Apr 2025 | North Ayrshire | 9.2 |
| Wee Minnemoer, Millport Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Feb 2024 | Feb 2023 | granted Feb 2024 | Feb 2024 | North Ayrshire | 9.3 |
Distance from the average position of the KA23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 5 | 0 | 2 | 1 | 0 | 20.6 |
| Wind farm | 14 | 1 | 1 | 6 | 3 | 107 |
| Wind turbine | 2 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 7 | 1 | 6 | 0 | 0 | 620 |
MW in pipeline: pending, approved and under-construction capacity.
How North Ayrshire decides solar, wind and battery applications
| Applications | North Ayrshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 12 (26%) | 19% |
| Solar refused | 1 of 18 | 12% |
| Onshore wind refused | 10 of 21 | 45% |
| Battery storage refused | 1 of 8 | 16% |
| Median time from submission to decision | 24.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 5 | — |
All projects in North Ayrshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.