Meiklelaught Farm (30 MW battery storage)

Meiklelaught Farm is a 30 MW battery storage project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 December 2023, not yet built; the record was last updated on 19 December 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
approved, not builtstatus in REPD
19 December 2023record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
12 October 2023Application submitted
13 December 2023Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
19 December 2023
Operator or applicant
Green Power Consultants
Planning authority
North Ayrshire
Planning application reference
23/00731/PPM
Address (REPD)
Meiklelaught Farm, Saltcoats
Council area (by location)
North Ayrshire
Time to decision
9 weeks
Name in REPD
Meiklelaught Farm - Battery Storage
REPD reference
14525

Who decides

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sorbie Farm wind clusterwind farm7.5application withdrawn1.4
Sorbie Farmwind farm9under construction1.4
Site To North East Of, Lochcraigs Farmsolar farm5operational1.9
Auld Claywind farm9.2refused2.1
Castlehill Solar Farmsolar farm5abandoned2.9
Ardeerwind farm22application withdrawn3.0
Ardrossanwind farm24operational3.5
Ardrossan Extensionwind farm6operational3.5
High Boydstone Farmbattery storage100approved, not built3.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6676, -4.7686).